Education On_going

Construction of 6-Unit Classroom Block at Accra

PRJ-25016

Project Overview

A project to improve infrastructure in Accra.

Total Budget
GHS 390,969.00
Start Date
Mar 09, 2025
Region
Eastern
MMDA
Lower Manya Krobo Municipal
Project Location
Map View
Citizen Feedback
M
Mr. Devin Rau compliment
6 months ago

Great work on the project! Delectus sint aspernatur reiciendis.

Official Response:

Thank you for your feedback.

J
Jeffry Paucek DVM compliment
7 months ago

Great work on the project! Maxime et ducimus quis nostrum tenetur.

Official Response:

Thank you for your feedback.

M
Maggie Herzog compliment
1 year ago

Great work on the project! Sit vitae aut id.

Official Response:

Thank you for your feedback.

Share your feedback
Project Timeline
Date TBD
Site Clearing & Preparation

Milestone for Site Clearing & Preparation

completed
Date TBD
Foundation Works

Milestone for Foundation Works

completed
Date TBD
Superstructure (Lintel Level)

Milestone for Superstructure (Lintel Level)

in progress
Date TBD
Roofing

Milestone for Roofing

pending
Date TBD
Plastering & Electricals

Milestone for Plastering & Electricals

pending
Date TBD
Finishing & Painting

Milestone for Finishing & Painting

pending
Date TBD
Handover

Milestone for Handover

pending
Key Dates
Kick-off: 09 Mar, 2025
Planned End: 02 Mar, 2026
Funding
Source: Internal Generated Fund